History of Sulwood Drive 2003-2022

The missing cycle path along Sulwood Drive between Tuggeranong Parkway and Athllon Drive has a long history. Letters to the Minister and Roads ACT go back as far as 2003. Labor promised a path for Sulwood Drive at the 2019 Federal Election, and ACT Labor reaffirmed this at the 2020 ACT Election. Funding was included for the path in the ACT 2021-2022 Budget.

ACT Projects Pipeline 2022 -23

The ACT Projects Pipeline gives you and idea what the ACT Government (Major Projects Canberra) thinks will be coming up. For cycling there is not much new here, except the 2022 ACT Household Travel Survey has officially started, 5 years after the last survey. Good news.

Molonglo 3 East staging

Molonglo 3 East is an area bigger than the built area of Write, Coombs and Denman Prospect combined. Just Stage 1 of Molonglo 3 East will likely take just as long to build as Whitlam stages 1, 2, and 3. Molonglo 3 East makes Whitlam look small. Five years for Molonglo 3 East Stage 1 and 20 years for Stages 1 to 4 in total. Stage 5 will come last and likely only after the East West Arterial is finished. Way off, in any case. By that time, Woden CIT and Light Rail Stage 2 (Woden) is finished. Canberra will not be the same place.

RobertsDay: Molonglo 3 East Planning and Infrastructure Study

The Molonglo 3 East Planning and Infrastructure Study is a combination of engineering (WSP) and urban design (RobertsDay). The content related to cycling is largely found in the reports written by RobertsDay. RobertsDay is facilitating a Movement and Place framework discussion between ACT Transport and ACT Environment on the go. Molonglo 3 East project is about experimentation and innovation. The cycle network is still inconclusive but appears promising.

WSP: Molonglo 3 East Planning and Infrastructure Study

The Molonglo 3 East Planning and Infrastructure Study is a combination of engineering (WSP) and urban design (RobertsDay). This article outlines what is in the report for cycling. This article focuses on the reports from WSP.

SMEC: East West Arterial / C10 City to Molonglo Cycleway

The Molonglo Valley has two arterial road corridors, one running east to west and the other north to south. The North South Arterial has been named John Gorton Drive. The East West Arterial (EWA) has yet to be named and expected to be completed before 2041. The East West Arterial includes a bridge over the Molonglo River and a new East West Arterial / Tuggeranong Parkway Interchange. The route is decided and traffic studies are underway.

Section 8.3 The curious case of rapid transit

This case study of rapid transit in the Molonglo Valley shows that corridors for vehicular traffic and light rail may have something in common, but public transit corridors are poorly suited for a cycle highway (transit). Cycle networks are different.

Tuggeranong, 1989: ahead of its time

After the paddocks in the Tuggeranong Valley, came suburbs and bike paths, and what beautiful bike paths they were. Here is a collection of vintage photographs from the ACT Archive taken in 1989.